Line 229: Line 229:
 
** Remove sink and plumbing
 
** Remove sink and plumbing
 
** Remove benches
 
** Remove benches
** Install toilet (and bathroom sink?) and new plumbing.
+
** Install toilet (and bathroom sink?) and new plumbing -- should be able to wait until after masonry.
** Install partition wall and door
+
** Install partition wall and door.
  
 
* DON'T FORGET LUNCH
 
* DON'T FORGET LUNCH
  
* Masonry -- wetroom first
+
* Masonry
 +
** 1 wetroom
 +
** 2 fill holes in walls
 +
** 3 finally block up connecting doorway
 
** ??? be very careful!  get everything sorted before mixing mortar
 
** ??? be very careful!  get everything sorted before mixing mortar
  

Revision as of 21:16, 19 April 2013

This is a list of things that need to be fixed or restored once we leave Cremer st. Please add anything you can think of, they will be struck off once we have confirmation that the work doesn't need to be done, or is completed.

I see a red door and I want to paint it black...

We need a door for the loo. The red door that was rescued from junking is now in the workshop, between the member box shelves and the machine tools, up against the wall. The holes have been patched and it's sanded. It needs to be painted, first with grey undercoat, and let to dry, second with black gloss. This will take a while because you can only paint one side at a time. I recommend using two sawhorses, and probably take it outside if it's nice out.

Paints for this are in one of the two bags stored on the last row of member box shelves in bags marked "for cremer restoration / do not use". There should be a clean brush soaking in the water in the shower room.

Things to keep in mind:

  • Clean off the brushes and close the paint tins after each coat and when finished! This paint should be quite easy to take off.
  • If you don't finish, update here with the time of the last coat so somebody else can pick up where you took off.
  • Don't forget the edges of the door!

Volunteer

Specialist:

chauffeur tgreer to help transport tools and building materials on saturday 11am-1pm
doorbot fixer member x to re-enable doorbot at cremer street so people can get in and out.

General labour:

  • aaron - all weekend 20-21
  • Will beaufoy - sunday

Supplies

The various supplies that have been bought and stored at the hackspace are on the last row of member box shelves in plastic bags with labels on them.

Supplies needed this weekend
Cleaning
buckets from hackspace 3 at least, as many as we can get
rags from hackspace infinity
henry already at cremer 1
paint scraper from hackspace 1
power sander + sandpaper from hackspace 1
bins for transporting tools from hackspace 3
Fixing holes in walls
screwdrivers from hackspace 2 posidriv, 1 phillips, 1 slotted
grippers from hackspace 3
putty knives from hackspace 3
pollyfilla bought 1 bucket (may need more)
work gloves from hackspace 3 pairs
Painting
brushes from hackspace, if clean / to buy 3 total
roller frames from hackspace 2
rollers to buy 2
trays to buy 1
coveralls from hackspace as many as we can borrow
white emulsion paint from space 2 huge buckets, to start
grey undercoat bought 1 litre
black gloss bought 1 litre
mineral spirits from hackspace / to buy 1 jug (litre?)
rubber gloves from hackspace / to buy 2 pairs
Rebuilding loo door
door itself at hackspace stored in workshop against wall between member boxes and machine tools.
Wood to buy
  • 100mm x 50mm planks: 2.8m x 2, 1m x 2 (or just 2.7m x 3)
  • door stop size: 2.8m x 3 (approx, can be shorter or longer)
Pane of wavy/frosted glass to buy ? NxM
Drill already at cremer 1
forstner bit set from hackspace 1
wood screws from hackspace various sizes
tape measure from hackspace 1
1/2" or 3/4" chisel from hackspace 1
level from hackspace 1
wood saw from hackspace 1
sawhorses from hackspace 2
hammer drill from hackspace 1
masonry drill set from hackspace 1
masonry screws from hackspace / to buy a bunch
wood plane from hackspace 1
Reinstalling loo window
pane of Georgian wired glass to buy NxM
glass sealant bought 1 canister
sandpaper from hackspace various
caulking gun from hackspace 1
Masonry (if we do it ourselves) -- we want type N mortar (1 part portlant cement, 1 part lime, 6 parts sand)
breeze blocks (440 x 215 x 100mm, low density should be ok) to buy from MP Building Supplies 54
contractor's (flat) shovel to buy 1
sheet of wood (for mortar) from space 1
bricklaying trowel to buy 1
cold chisel from space 1
lump hammer from space 1
brick jointer to buy 1,
portland cement to buy 2 x 25kg bags
aggregate to buy 5 x 25kg bags
plasticiser cursory search at cremer, otherwise to buy 24 ml
Fixing holes in front door
wall filler bought 1 small tin
Removing Kitchen
tools already included
Plumbing
adjustable spanner from hackspace 1
???
Fixing holes in front door
scrap wood from space several pieces
wood saw from space 1
drill already at cremer 1
wood drill set from hackspace 1
screwdriver bit from hackspace assortment
wood screws from hackspace various
Misc
hammer from space 1
scrap lumber from space several pieces
short ladder from space 1
newspapers or plastic sheeting from space 1

Prep still to do

Checklist for weekend 20-21

  • Gather everything we can from Cremer street in wee hours of morning.
  • Bring cleaning supplies and basic tools to Cremer so people can start.
  • Load everything else in van with tgreer and bring to Cremer.
  • Pick up new supplies and bring to Cremer -- MP building suppliers and Jewsons (if necessary)
  • Cleaning
    • Clean walls
    • Clean sinks
    • Repair holes in walls
  • Painting red door black
    • see above
  • Wetroom
    • Remove sink and plumbing
    • Remove benches
    • Install toilet (and bathroom sink?) and new plumbing -- should be able to wait until after masonry.
    • Install partition wall and door.
  • DON'T FORGET LUNCH
  • Masonry
    • 1 wetroom
    • 2 fill holes in walls
    • 3 finally block up connecting doorway
    • ??? be very careful! get everything sorted before mixing mortar
  • General painting -- AFTER WETROOM DONE
    • Paint walls and entrance door
    • Paint partition wall

Checklist for weekend 27-28

  • Finish plumbing
  • ???
  • Remove doorbot and repair holes in door

Water Stopcock locations

In unit 23, in the corner where the member boxes were. In unit 24, in cupboard next to the toilet.

Toilets

  • Paint all walls white in toilets.
  • Paint toilet doors black.
  • biolab/darkroom - Remove sink and shelving/work surface, restore partition (and door ?), and replace loo and basin that have been removed and stored.

Unit 24

  • Repair holes in front door/remove camera from spy hole and outside door.
  • Restore connecting wall to 23.
  • Replace kitchen sink in original location, which was under the laptop bar: on the right as you walk into the main room of 24.
  • Remove everything else in kitchen.
  • Remove waste pipe to 23.
  • Wash concrete block walls, fill holes, and paint where necessary.
  • Collect decorative electrical panels - one by front door, possibly one by kitchen door.

Unit 23

  • Fit new glass where extraction for lasercutter is currently.
  • Fill in hole where the duct comes through the wall from the workshop.
  • Wash concrete block walls, fill holes, and paint where necessary.

Outside

  • Sweep balconies for any items.

Measurements

  • Size of breeze blocks: 440 x 215 x 100mm
  • inter-unit doorway approx size: 1170 x 2240mm
  • new door to be installed in loo: 686 x 1981mm
  • height of ceiling in loo -- to be measured (may be uneven)
  • approx area to brick up in loo: 1000 x 2700mm
  • door frame timber: 50x100mm
  • external loo window to fix: 854mm x 232 mm -- someone should double-check before ordering

Suppliers

 MP Building Supplies
 282 Cambridge Heath Road, Bethnal Green