== Cremer St Preparations ==
+
'''Important:''' this is not authoritative. It's just a guideline for people who want to understand what's remaining.  Please speak to the [[http://wiki.london.hackspace.org.uk/view/Hackspace_Move#Key_Projects|project contacts]] to find out what the current state is.
 +
 
 +
== [[Hackspace_Move/Cremer_Restoration|Cremer St Preparations]] ==
  
 
* Agree on Cremer St restoration with landlord
 
* Agree on Cremer St restoration with landlord
Line 20: Line 22:
 
** FTTC internet ordered from Zen
 
** FTTC internet ordered from Zen
  
== Hackney Road build-out ==
+
Decisions
 +
* [[Hackspace_Move/Layout|Finalise layout]]
 +
 
 +
== [[Hackspace_Move/Renovation|Hackney Road build-out]] ==
 
* Install the large classroom walls. Not totally necessary, but it might be tricky to have any of our regular meetings without it.
 
* Install the large classroom walls. Not totally necessary, but it might be tricky to have any of our regular meetings without it.
 
* Get a lift engineer out to verify that the lift really is safe to use and place heavy loads in.
 
* Get a lift engineer out to verify that the lift really is safe to use and place heavy loads in.
Line 26: Line 31:
 
* Install plywood panel(s) in current grill Fire Exit door in basement to stop all the heat escaping outdoors [http://www.flickr.com/photos/hllns/8386735403/ (Pic)]
 
* Install plywood panel(s) in current grill Fire Exit door in basement to stop all the heat escaping outdoors [http://www.flickr.com/photos/hllns/8386735403/ (Pic)]
  
== Hackney Road move ==
+
== [[Hackspace_Move/Logistics|Hackney Road move]] ==
  
 
* Obtain/make equipment for move and fit-out. Moving skates made from scrap wood and castors, Larger ladder for access in new space which has quite a high ceiling
 
* Obtain/make equipment for move and fit-out. Moving skates made from scrap wood and castors, Larger ladder for access in new space which has quite a high ceiling

Revision as of 14:14, 23 March 2013

Important: this is not authoritative. It's just a guideline for people who want to understand what's remaining. Please speak to the [contacts] to find out what the current state is.

Cremer St Preparations

  • Agree on Cremer St restoration with landlord
  • Cremer St cleanup
  • Our Cremer Street lease ends on the 30th April
  • We need Cremer street to be clear so we can restore it by the 20th/21st April, but 13th/14th would be better.

Hackney Road preparations

Access

  • Get a locksmith to fit an electronic release on the back door.
  • Get override keys cut for every trustee for the back door release.
  • Get doorbot installed on the back door, running on an offline card DB. (Looking at Jasper, Mark and Charles here)

Services

  • Russ: take initial water & gas meter readings
  • organise rubbish collection (get a skip?)
  • Get an internet connection working - this may also require a phone line connecting, although I have a vague memory of Jasper saying the phone was already connected. Basic wifi follows on from this. (Jasper?)
    • Phone lines are connected by still being paid for, so we can't take them over. New line will be fitted 27/3/2013
    • FTTC internet ordered from Zen

Decisions

Hackney Road build-out

  • Install the large classroom walls. Not totally necessary, but it might be tricky to have any of our regular meetings without it.
  • Get a lift engineer out to verify that the lift really is safe to use and place heavy loads in.
  • Install ventilation downstairs, routed outside. (Charles?)
  • Install plywood panel(s) in current grill Fire Exit door in basement to stop all the heat escaping outdoors (Pic)

Hackney Road move

  • Obtain/make equipment for move and fit-out. Moving skates made from scrap wood and castors, Larger ladder for access in new space which has quite a high ceiling
  • Start setting up workspaces, workshop, shelves
  • MOVE ALL THE THINGS
  • Deadline : 20th/21st April, but 13th/14th would be better

PHASE X: Not Time Critical

  • organise water & gas