447 Power: Difference between revisions

From London Hackspace Wiki
m (clarify which)
No edit summary
Line 11: Line 11:
Existing lighting remains in situ, along with some wall sockets (mostly at main stairs end).  New circuits will be provisioned via new distribution boxes as follows:
Existing lighting remains in situ, along with some wall sockets (mostly at main stairs end).  New circuits will be provisioned via new distribution boxes as follows:


'''Box A''': All power, except overhead lighting circuits, which is used in the wood workshop. Individual circuits for major equipment plus one 'general sockets'. As appropriate, mushroom STOP buttons to be installed for dangerous equipment ([[User:Solexious]] is co-ordinating)
'''Box A''': All power, except overhead lighting circuits, which is used in the wood workshop. ([[User:Solexious]] is co-ordinating)


'''Box B''': All power, except overhead lighting circuits, which is used in the metal workshop. Individual circuits for major equipment plus one 'general sockets'. As appropriate, mushroom STOP buttons to be installed on dangerous equipment. ([[User:Solexious]] is co-ordinating)
'''Box B''': All power, except overhead lighting circuits, which is used in the metal workshop. ([[User:Solexious]] is co-ordinating)


'''Box C''': All power, except overhead lighting circuits, which is used in the biolab and wet room (darkroom). Biolab circuits per their request.
'''Box C''': All power, except overhead lighting circuits, which is used in the biolab and wet room (darkroom). Biolab circuits per their request.


'''Box D''': Power circuits, except overhead lighting, for equipment in general workshop area. Major equipment (eg. lathes) on individual circuits, with mushroom STOP buttons at point nearest central gangway ''or'' on wall (tbc). ([[User:Solexious]] co-ordinating)
'''Box D''': Power circuits, except overhead lighting, for equipment in general workshop area. ([[User:Solexious]] co-ordinating)


'''Box E''': 3-phase 16A power circuit. Not in current use,
'''Box E''': 3-phase 16A power circuit. Not in current use,
Line 35: Line 35:


===Distribution details===
===Distribution details===
All sub-distribution boxes are supplied via 12mm^2 csa per core armoured cable, unless stated.
All sub-distribution boxes are supplied via 12mm^2 csa per core armoured or non-armoured cable, unless stated.


;Box A:
;Box A:
Line 44: Line 44:


;Box C:
;Box C:
:Biolab circuits: 12 double sockets on two circuits,  RCD-protected, 4 double sockets on single circuit, no RCD.
:Biolab circuits: 16 double sockets on three circuits,  RCD-protected,  
:Wet room: presently undefined: two MCB spaces reserved, all RCD-protected. One 6A lighting circuit.
:Wet room: presently undefined: two MCB spaces reserved, all RCD-protected. One 6A lighting circuit.
::Total requirement: incomer, 2RCDs, 8 MCBs (6,10,32x2), 2blank - 14 ways total - standard CU products can be used
::Total requirement: incomer, 2RCDs, 6 MCBs (6,32x3, 2blank) - 12 ways total - standard CU products can be used
   
   
;Box D:
;Box D:
Line 55: Line 55:


;Box F:
;Box F:
:Server: 16A outlet, 1x double socket, no RCD. sep circuits.
:Server: 2x 16A outlet, 1x double socket, RCD. sep circuits.
:CNC: presently undefined: 4 MCB spaces plus 2 for RCD reserved.
:CNC: presently undefined: 4 MCB spaces plus 2 for RCD reserved.
:two circuits for expansion (''room opp boiler entrance?'')
:two circuits for expansion (''room opp boiler entrance?'')
::Total requirement: incomer:2 MCBs (16x2), 8blank - 10 ways total - standard CU products can be used
::Total requirement: incomer:2 MCBs (10,16x2, 8blank) - 15 ways total - standard CU products can be used


;Box J:
;Box J:
Line 66: Line 66:


;Box K: '''This circuit and box will not be installed until a decision is final on whether a second room is being built here.'''
;Box K: '''This circuit and box will not be installed until a decision is final on whether a second room is being built here.'''
:'''on hold''' pending better definition of area requirements. Will require one RCD for inside and one for outside.
:'''on hold''' pending better definition of area requirements. Will require one RCD for inside and one for outside, though latter may be local to exit with switch.
::Install 10-way CU as default; MCB choices can be revised subsequently.
::Install 10-way CU as default; MCB choices can be revised subsequently.



Revision as of 09:38, 4 April 2013

Power General Notes:

  1. Existing 230V/13A wall sockets should only be used for low-current equipment, not large items. The latter will have a separate supply
  2. New circuits will be installed with local distribution boxes so that there should never be a need to access the main electrical intake room (which belongs to the landlord, not us)
  3. Re safety emergency buttons (eg. RS 330-8559) they can be fitted per item of equipment or per room. There is a strong argument that if someone away from the area where the emergency occurs runs to offer help they don't want to have to work out which kit is the problem, and that therefore the room power should be killed as a 'safety-first' issue. Latest discussions are that there will be a 'room' one external to the new workshop rooms, with some 'item' ones inside. Further comments welcome.
  4. Maintained emergency exit signs will be located as per plan (at least). There are already emergency lights in place covering the whole floor which have been tested.
  5. If in doubt, talk to User:AlisonW. If you need something special in your area, talk to User:AlisonW. If you think this is wrong, talk to User:AlisonW!

Basement

Basement elec.png

Existing lighting remains in situ, along with some wall sockets (mostly at main stairs end). New circuits will be provisioned via new distribution boxes as follows:

Box A: All power, except overhead lighting circuits, which is used in the wood workshop. (User:Solexious is co-ordinating)

Box B: All power, except overhead lighting circuits, which is used in the metal workshop. (User:Solexious is co-ordinating)

Box C: All power, except overhead lighting circuits, which is used in the biolab and wet room (darkroom). Biolab circuits per their request.

Box D: Power circuits, except overhead lighting, for equipment in general workshop area. (User:Solexious co-ordinating)

Box E: 3-phase 16A power circuit. Not in current use,

Box F: Power for server stack, future CNC workshop, and additional circuits.

Ground Floor

Partitions to be added

This will be similar to downstairs in terms of getting the power to needed areas, though there are more socket points already in situ; New local distribution boxes are as follows:

Box J: Supplies sockets in local work area and (part of) central area. Also supplies emergency exit lighting above stairs and at main entrance.

Box K: Supplies sockets and equipment in local area (probably electronics lab) and circuit to outside (via separate local RCD).

Box L: Supplies the two socket rings in the new classroom, plus (part of) central area. Also supplies emergency exit lighting at each end of corridor.

Distribution details

All sub-distribution boxes are supplied via 12mm^2 csa per core armoured or non-armoured cable, unless stated.

Box A
User:Solexious
Box B
User:Solexious
Box C
Biolab circuits: 16 double sockets on three circuits, RCD-protected,
Wet room: presently undefined: two MCB spaces reserved, all RCD-protected. One 6A lighting circuit.
Total requirement: incomer, 2RCDs, 6 MCBs (6,32x3, 2blank) - 12 ways total - standard CU products can be used
Box D
User:Solexious
Box E
Termination only.
Box F
Server: 2x 16A outlet, 1x double socket, RCD. sep circuits.
CNC: presently undefined: 4 MCB spaces plus 2 for RCD reserved.
two circuits for expansion (room opp boiler entrance?)
Total requirement: incomer:2 MCBs (10,16x2, 8blank) - 15 ways total - standard CU products can be used
Box J
partially on hold pending better definition of area requirements
Emergency exit lights 6A
Total requirement: incomer, 5 circuits with RCB - min 8 ways total - standard CU products can be used
Box K
This circuit and box will not be installed until a decision is final on whether a second room is being built here.
on hold pending better definition of area requirements. Will require one RCD for inside and one for outside, though latter may be local to exit with switch.
Install 10-way CU as default; MCB choices can be revised subsequently.
Box L
Classroom: 2 rings to extant fittings. RCD-protected
Emergency Exit lights: 6A
install 6-way sub-CU, using twin+earth not armoured (due to routing required)