Hackspace Move/Timeline: Difference between revisions

From London Hackspace Wiki
No edit summary
Line 6: Line 6:
* Cremer St cleanup
* Cremer St cleanup
* Our Cremer Street lease ends on the '''30th April'''
* Our Cremer Street lease ends on the '''30th April'''
* We need Cremer street to be clear so we can restore it by the 20th/21st April, but 13th/14th would be better.
* We need Cremer street to be clear so we can restore it by the 13th/14th  


== Hackney Road preparations ==
== Hackney Road preparations ==
Line 37: Line 37:
* Start setting up workspaces, workshop, shelves
* Start setting up workspaces, workshop, shelves
* MOVE ALL THE THINGS
* MOVE ALL THE THINGS
* '''Deadline''' : 20th/21st April, but 13th/14th would be better
* '''Deadline''' : 13th/14th April


== PHASE X: Not Time Critical ==
== PHASE X: Not Time Critical ==


* organise water & gas
* organise water & gas

Revision as of 00:22, 24 March 2013

Important: this is not authoritative. It's just a guideline for people who want to understand what's remaining. Please speak to the [contacts] to find out what the current state is.

Cremer St Preparations

  • Agree on Cremer St restoration with landlord
  • Cremer St cleanup
  • Our Cremer Street lease ends on the 30th April
  • We need Cremer street to be clear so we can restore it by the 13th/14th

Hackney Road preparations

Access

  • Get a locksmith to fit an electronic release on the back door.
  • Get override keys cut for every trustee for the back door release.
  • Get doorbot installed on the back door, running on an offline card DB. (Looking at Jasper, Mark and Charles here)

Services

  • Russ: take initial water & gas meter readings
  • organise rubbish collection (get a skip?)
  • Get an internet connection working - this may also require a phone line connecting, although I have a vague memory of Jasper saying the phone was already connected. Basic wifi follows on from this. (Jasper?)
    • Phone lines are connected by still being paid for, so we can't take them over. New line will be fitted 27/3/2013
    • FTTC internet ordered from Zen

Decisions

Hackney Road build-out

  • Install the large classroom walls.
  • Get a lift engineer out to verify that the lift really is safe to use and place heavy loads in.
  • Install ventilation downstairs, routed outside. (Charles?)
  • Change current Fire Exit door in basement so it's solid rather than a grill, possibly by panelling with plywood (Pic)
  • Networking, including patch panels downstairs

Hackney Road move

  • Obtain/make equipment for move and fit-out. Moving skates made from scrap wood and castors, Larger ladder for access in new space which has quite a high ceiling
  • Start setting up workspaces, workshop, shelves
  • MOVE ALL THE THINGS
  • Deadline : 13th/14th April

PHASE X: Not Time Critical

  • organise water & gas