Hackspace Move/Cremer Restoration: Difference between revisions
From London Hackspace Wiki
Line 18: | Line 18: | ||
* Fit new glass where extraction for lasercutter is currently | * Fit new glass where extraction for lasercutter is currently | ||
* Fill in hole where the duct comes through the wall from the workshop. | * Fill in hole where the duct comes through the wall from the workshop. | ||
* Paint | * Paint all walls back to white | ||
==Outside== | ==Outside== | ||
* Sweep balconies for any items | * Sweep balconies for any items |
Revision as of 18:01, 10 March 2013
This is a list of things that need to be fixed or restored once we leave Cremer st. Please add anything you can think of, they will be struck off once we have confirmation that the work doesn't need to be done, or is completed.
Unit 24
- Restore connecting wall to 23
- Restore kitchen
- Replace ceiling tiles
- Paint all walls white in main rooms
- Paint all walls white in toilets
- Paint toilet doors black
- Remove internal walls and false ceiling
- Remove waste pipe to 23
- Remove plastic strips
- Repair holes in front door
Unit 23
- Fix holes in back door
- Restore partition in loo and replace any loos or basins that have been removed
- Fit new glass where extraction for lasercutter is currently
- Fill in hole where the duct comes through the wall from the workshop.
- Paint all walls back to white
Outside
- Sweep balconies for any items