Line 30: | Line 30: | ||
* Install ventilation downstairs, routed outside. (Charles?) | * Install ventilation downstairs, routed outside. (Charles?) | ||
* Install plywood panel(s) in current grill Fire Exit door in basement to stop all the heat escaping outdoors [http://www.flickr.com/photos/hllns/8386735403/ (Pic)] | * Install plywood panel(s) in current grill Fire Exit door in basement to stop all the heat escaping outdoors [http://www.flickr.com/photos/hllns/8386735403/ (Pic)] | ||
* Wall off entire fire exit door in basement | |||
== [[Hackspace_Move/Logistics|Hackney Road move]] == | == [[Hackspace_Move/Logistics|Hackney Road move]] == |
Revision as of 14:15, 23 March 2013
Important: this is not authoritative. It's just a guideline for people who want to understand what's remaining. Please speak to the [contacts] to find out what the current state is.
Cremer St Preparations
- Agree on Cremer St restoration with landlord
- Cremer St cleanup
- Our Cremer Street lease ends on the 30th April
- We need Cremer street to be clear so we can restore it by the 20th/21st April, but 13th/14th would be better.
Hackney Road preparations
Access
Get a locksmith to fit an electronic release on the back door.- Get override keys cut for every trustee for the back door release.
Get doorbot installed on the back door, running on an offline card DB. (Looking at Jasper, Mark and Charles here)
Services
Russ: take initial water & gas meter readings- organise rubbish collection (get a skip?)
- Get an internet connection working - this may also require a phone line connecting, although I have a vague memory of Jasper saying the phone was already connected. Basic wifi follows on from this. (Jasper?)
- Phone lines are connected by still being paid for, so we can't take them over. New line will be fitted 27/3/2013
- FTTC internet ordered from Zen
Decisions
Hackney Road build-out
- Install the large classroom walls. Not totally necessary, but it might be tricky to have any of our regular meetings without it.
- Get a lift engineer out to verify that the lift really is safe to use and place heavy loads in.
- Install ventilation downstairs, routed outside. (Charles?)
- Install plywood panel(s) in current grill Fire Exit door in basement to stop all the heat escaping outdoors (Pic)
- Wall off entire fire exit door in basement
Hackney Road move
- Obtain/make equipment for move and fit-out. Moving skates made from scrap wood and castors, Larger ladder for access in new space which has quite a high ceiling
- Start setting up workspaces, workshop, shelves
- MOVE ALL THE THINGS
- Deadline : 20th/21st April, but 13th/14th would be better
PHASE X: Not Time Critical
- organise water & gas