Hackspace Move/Timeline
From London Hackspace Wiki
PHASE 1: Preparations
- agree on Cremer St restoration with landlord
- Cremer St cleanup
PHASE 2: We receive Keys
Access
- Get a locksmith to fit an electronic release on the back door.
- Get override keys cut for every trustee for the back door release.
- Get doorbot installed on the back door, running on an offline card DB. (Looking at Jasper, Mark and Charles here)
Infrastructure
- Get a lift engineer out to verify that the lift really is safe to use and place heavy loads in.
- Install ventilation downstairs, routed outside. (Charles?)
- Install plywood panel(s) in current grill Fire Exit door in basement to stop all the heat escaping outdoors (Pic)
Services
- Russ: take initial water & gas meter readings
- organise rubbish collection (get a skip?)
- Get an internet connection working - this may also require a phone line connecting, although I have a vague memory of Jasper saying the phone was already connected. Basic wifi follows on from this. (Jasper?)
PHASE 3: We have Fitted Locks & Doorbot
- Obtain/make equipment for move and fit-out. Moving skates made from scrap wood and castors, Larger ladder for access in new space which has quite a high ceiling
- Start setting up workspaces, workshop, shelves
- MOVE ALL THE THINGS
PHASE X: Not Time Critical
- organise water & gas
- Possibly install the large classroom walls. Not totally necessary, but it might be tricky to have any of our regular meetings without it.