== [[Hackspace_Move/Renovation|Hackney Road build-out]] ==
 
== [[Hackspace_Move/Renovation|Hackney Road build-out]] ==
 
* Install the large classroom walls.
 
* Install the large classroom walls.
* Get a lift engineer out to verify that the lift really is safe to use and place heavy loads in.
+
<s>* Get a lift engineer out to verify that the lift really is safe to use and place heavy loads in.</s>Insurance issues still to be addressed
 
* Install ventilation downstairs, <s>routed outside.</s> (Charles?)
 
* Install ventilation downstairs, <s>routed outside.</s> (Charles?)
* Change current Fire Exit door in basement so it's solid rather than a grill, possibly by panelling with plywood [http://www.flickr.com/photos/hllns/8386735403/ (Pic)]
+
<s>* Change current Fire Exit door in basement so it's solid rather than a grill, possibly by panelling with plywood [http://www.flickr.com/photos/hllns/8386735403/ (Pic)]</s>
 
* Wall off entire fire exit door in basement
 
* Wall off entire fire exit door in basement
 
* Networking, including patch panels downstairs
 
* Networking, including patch panels downstairs

Revision as of 18:01, 2 April 2013

Important: this is not authoritative. It's just a guideline for people who want to understand what's remaining. Please speak to the [contacts] to find out what the current state is.

Cremer St Preparations

  • Agree on Cremer St restoration with landlord
  • Cremer St cleanup
  • Our Cremer Street lease ends on the 30th April
  • We need Cremer street to be clear so we can restore it by the 13th/14th

Hackney Road preparations

Access

  • Get a locksmith to fit an electronic release on the back door.
  • Get override keys cut for every trustee for the back door release.
  • Get doorbot installed on the back door, running on an offline card DB. (Looking at Jasper, Mark and Charles here)

Services

  • Russ: take initial water & gas meter readings Eletric?
  • organise rubbish collection (get a skip?)
  • Get an internet connection working - this may also require a phone line connecting, although I have a vague memory of Jasper saying the phone was already connected. Basic wifi follows on from this. (Jasper?)
    • Phone lines are connected by still being paid for, so we can't take them over. New line will be fitted 27/3/2013
    • FTTC internet ordered from Zen

Decisions

Hackney Road build-out

  • Install the large classroom walls.

* Get a lift engineer out to verify that the lift really is safe to use and place heavy loads in.Insurance issues still to be addressed

  • Install ventilation downstairs, routed outside. (Charles?)

* Change current Fire Exit door in basement so it's solid rather than a grill, possibly by panelling with plywood (Pic)

  • Wall off entire fire exit door in basement
  • Networking, including patch panels downstairs

Hackney Road move

  • Obtain/make equipment for move and fit-out. Moving skates made from scrap wood and castors, Larger ladder for access in new space which has quite a high ceiling
  • Start setting up workspaces, workshop, shelves
  • MOVE ALL THE THINGS
  • Deadline : 13th/14th April

PHASE X: Not Time Critical

  • organise water & gas