Hackspace Move/Planning/2013-03-25: Difference between revisions

From London Hackspace Wiki

m
Line 25: Line 25:
The old office/counter on the ground floor was demolished. We received a first delivery: plasterboard, rock wool, etc. We're expecting 2x4s on Tuesday so we can build it, delivery time 8-11am.
The old office/counter on the ground floor was demolished. We received a first delivery: plasterboard, rock wool, etc. We're expecting 2x4s on Tuesday so we can build it, delivery time 8-11am.


Paddy, Steve, Chris, Charles etc will start setting up the walls tomorrow, once everything has been delivered.
Paddy, Steve, Chris, Charles etc will start setting up the walls on Tuesday, once everything has been delivered.


== Ventilation ==
== Ventilation ==