== | == Weekend volunteer list: Sat/Sun 27/28 April == | ||
If you can help out please add yourselves below. It's easy, it's gratifying work, and it ensures we get back our £7,000 deposit. We'll try to make sure that there's always someone around to provide guidance. | |||
Masonry is done (just some dressing needed, and filling holes), now there's lots of painting to do, a little bit of plumbing, a seemingly infinite number of other little details, and a big cleanup when it's all done. (Note that the "what's left" list on this page may not be up to date any more. Simon sent an [https://groups.google.com/d/msg/london-hack-space/bIPGVaS76us/SYP13SnUAi0J update on Thursday night].) | |||
== What's left == | == What's left == | ||
Line 37: | Line 9: | ||
This is a list of things that need to be fixed or restored once we leave Cremer st. Please add anything you can think of, they will be <s>struck off</s> once we have confirmation that the work doesn't need to be done, or is completed. | This is a list of things that need to be fixed or restored once we leave Cremer st. Please add anything you can think of, they will be <s>struck off</s> once we have confirmation that the work doesn't need to be done, or is completed. | ||
NOTE: | NOTE: YOU WILL NEED THE KEY TO UNIT 23 TO GET IN. THIS IS HUNG UP INSIDE THE CABINET ON THE LEFT COMING INTO UNIT 24. | ||
{| class="wikitable" | {| class="wikitable" | ||
Line 61: | Line 33: | ||
! 23-L !! status | ! 23-L !! status | ||
|- | |- | ||
| Replace window || | | <s>Replace window</s> || done | ||
|- | |- | ||
! 23-R !! status | ! 23-R !! status | ||
|- | |- | ||
| HIGH PRIORITY: Finish block wall ( | | <s>HIGH PRIORITY: Finish block wall</s> || done (still needs painting) | ||
|- | |- | ||
| cut and cap grey pipe blocking access to quiet room hole || | | <s>cut and cap grey pipe blocking access to quiet room hole</s> || done | ||
|- | |- | ||
| Patch hole to quiet room || | | <s>Patch hole to quiet room</s> || done-needs skimming once motar set | ||
|- | |- | ||
| install window above inner door (see instructions) || | | <s>install window above inner door (see instructions)</s> || | ||
|- | |- | ||
| remove and paint inner door - use grey undercoat first, and don't forget edges || | | <s>remove and paint inner door - use grey undercoat first, and don't forget edges</s> || done | ||
|- | |- | ||
| install strike plate for inner door (spade drills and chisel are there) || | | install strike plate for inner door (spade drills and chisel are there) || | ||
Line 79: | Line 51: | ||
| replace inner door (after painting) || | | replace inner door (after painting) || | ||
|- | |- | ||
| Add beading/doorstop/strip (whatever you call it) for inner door || | | <s>Add beading/doorstop/strip (whatever you call it(intumesent strip?)) for inner door</s> || done | ||
|- | |- | ||
| install toilet (may be in 23-L) || | | <s>install toilet (may be in 23-L)</s> || done | ||
|- | |- | ||
| Create stand for sink out of lumber. (sink is probably stored in adjacent loo) It's quite heavy and won't be adequately supported by attaching to the wall. || | | <s>Create stand for sink out of lumber. (sink is probably stored in adjacent loo) It's quite heavy and won't be adequately supported by attaching to the wall. No, sink brackets were inside toilet cistern</s> || done | ||
|- | |- | ||
| install plumbing for sink || | | <s>install plumbing for sink</s> || done | ||
|- | |- | ||
! 24-L !! status | ! 24-L !! status | ||
Line 93: | Line 65: | ||
! 24-R !! status | ! 24-R !! status | ||
|- | |- | ||
| remove stickers from toilet || | | <s>remove stickers from toilet</s> || | ||
|- | |- | ||
| clean toilet, if it still looks shit, repaint it black || | | <s>clean toilet, if it still looks shit, repaint it black</s> || | ||
|- | |- | ||
| Repair flush mechanism on toilets || | |||
|} | |} | ||
Line 103: | Line 76: | ||
! Task !! Status | ! Task !! Status | ||
|- | |- | ||
| HIGH PRIORITY: Finish block wall between 23 and 24 (see howtos -- this is hard, requires 2 people!) || | | <s>HIGH PRIORITY: Finish block wall between 23 and 24(see howtos -- this is hard, requires 2 people!)</s> || Done | ||
|- | |- | ||
| unit | | <s>HIGH PRIORITY: Fill square hole in unit 23</s> || done | ||
|- | |- | ||
| <s> | | <s>unit 24 -- build simple counter supported by frame made from 2x4 timber and install sink in original location, outside loo 23-L. Will need jigsaw from newspace.</s> || done | ||
|- | |- | ||
| Kitchen -- | | <s>Kitchen -- remove cabinets non-destructively, we want them.</s> || done | ||
|- | |- | ||
| Kitchen -- wash nasty wall and windowsills, and repaint || | | <s>Kitchen -- wash nasty wall and windowsills, and repaint</s> || | ||
|- | |- | ||
| unit 24 -- plug/fill hole in front door where camera was || | | <s>unit 24 -- plug/fill hole in front door where camera was</s> || done-needs sanding | ||
|- | |- | ||
| hoover/clean loo floors -- this will give good impression to landlord for very little work. || | | hoover/clean loo floors -- this will give good impression to landlord for very little work. || | ||
Line 123: | Line 94: | ||
| tidy everything up inside, remove rubbish -- junk left behind will probably be removed by landlord at our expense || | | tidy everything up inside, remove rubbish -- junk left behind will probably be removed by landlord at our expense || | ||
|- | |- | ||
| unit 24 -- remove doorbot and patch hole with wood, then fill edges with wood filler (brown stuff). This should be done as late as possible, but you can make the wood patch by taking | | unit 24 -- remove doorbot card reader and patch hole with wood, then fill edges with wood filler (brown stuff). This should be done as late as possible, but you can make the wood patch by taking reader out temporarily, and only put it in as the last step. || | ||
|- | |||
| Remove CISA release lock from door to unit 24, remove doorbot and bell from wall above the meter || | |||
|- | |||
| Paint remaining parts of the wall around meter and behind old payphone and where the wall has been filled at the back of the quiet room || | |||
|} | |} | ||
Line 130: | Line 105: | ||
{| class="wikitable" | {| class="wikitable" | ||
|+ Supplies still needed | |+ Supplies still needed | ||
|- | |- | ||
| door spindle (square rod) and 2 handles - i've got 1 handle and sq. rod from the old space || hardware store | | door spindle (square rod) and 2 handles - i've got 1 handle and sq. rod from the old space || hardware store | ||
|- | |- | ||
| panel pins for door stop || hardware store | | panel pins for door stop || hardware store | ||
|} | |} | ||
Line 209: | Line 174: | ||
Breeze blocks, sand, cement, wood can come from: | Breeze blocks, sand, cement, wood can come from: | ||
MP Building Supplies | MP Building Supplies | ||
282 Cambridge Heath Road, Bethnal Green | 282 Cambridge Heath Road, Bethnal Green (google maps is wrong! actually at intersection with Old Bethnal Green Road) | ||
London, E2 9HA | London, E2 9HA | ||
020 7729 1699 | 020 7729 1699 | ||
Line 219: | Line 184: | ||
Fri: 07:00 - 17:00 | Fri: 07:00 - 17:00 | ||
Sat: 08:00 - 14:00 | Sat: 08:00 - 14:00 | ||
[[Category:Moving_Space]] |