(Created page with "* Description: wiring for oven anoff M12 full nuts 4 off M12 flat washers (on site) 4 off M10 studding 350mm d hob. Needs to be done by a competent person. * People: Russ, Paddyd...")
 
No edit summary
Line 11: Line 11:
* Distro box: 3x32A breakers, 1x16A breaker
* Distro box: 3x32A breakers, 1x16A breaker
* Cables:
* Cables:
{|
{| class="wikitable"
! Purpose !! Power !! Diameter
! Purpose !! Power !! Diameter !! Length
|-
|-
| Cable to distro | 100A || 16mm
| Distro || 100A || 16mm ||
|-
|-
| Cable to oven | 5kW (>>22A) || 4mm
| Oven || 5kW (>>22A) || 4mm ||
|-
|-
| Cable to hob | 6kW/6.6kW (>>29A) || 4mm
| Hob || 6kW/6.6kW (>>29A) || 4mm ||
|-
|-
| Cable to water heater | guess 3kW (13A) || 2.5mm
| Water heater || guess 3kW (13A) || 2.5mm ||
|-
|-
| Ring main |  | 2.5mm
| Ring main ||| 2.5mm ||
|}
|}


Upgrade all cross-sections (2.5-4, 4-6, 16-25) if not clipped to a masonry or wooden wall.
Upgrade all diameters (2.5-4, 4-6, 16-25) if not clipped to a masonry or wooden wall.


=== Suggested suppliers===
=== Suggested suppliers===

Revision as of 23:20, 15 February 2012

  • Description: wiring for oven anoff M12 full nuts

4 off M12 flat washers (on site) 4 off M10 studding 350mm d hob. Needs to be done by a competent person.

  • People: Russ, Paddyd, Phil


We have sockets and 2.5mm cable aplenty.

Planned

  • Distro box: 3x32A breakers, 1x16A breaker
  • Cables:
Purpose Power Diameter Length
Distro 100A 16mm
Oven 5kW (>>22A) 4mm
Hob 6kW/6.6kW (>>29A) 4mm
Water heater guess 3kW (13A) 2.5mm
Ring main 2.5mm

Upgrade all diameters (2.5-4, 4-6, 16-25) if not clipped to a masonry or wooden wall.

Suggested suppliers

  • TLC-direct (cheap, but whole drum)
  • ?


Back-up option

  • 2x4mm spurs, one for hob, one for oven
  • Leave boiler on electric circuit or do a separate 2.5/4mm run for that.