== Physical | == Layer 1 (Physical Wiring) == | ||
=== Ground Floor === | === Ground Floor === | ||
Line 83: | Line 83: | ||
=== First Floor === | === First Floor === | ||
[[File:1st floor network.png|thumbnail|Rough diagram showing path of network cables above the ceiling of the 1st floor.]] | |||
* 2x Cat6 cables from the ground floor cabinet go up the cable riser and then run above the ceiling tiles into the server room, in cable tray some of the way, see image. | |||
* There are a large number of network sockets spread around the 1st floor, many (all?) of which seem to be run back to a large bundle of cables in the server room, some (all?) of which also run above the ceiling in cable trays. | |||
==== Patch Panel ==== | ==== Patch Panel ==== |
Revision as of 01:04, 11 July 2018
This is the networking page for Ujima House the 2018-era planned location for London Hackspace. An active IT infrastructure planning document is being worked on in Google Sheets.
We want your help! Please reach out on the LHS Infrastructure IRC channel or post on the London Hackspace Infrastructure Google Group if you'd like to get involved.
For historical comparison, please refer to 447 Networking.
Our ISP
- What is the broadband availability at the place? Is there fibre already?
According to the SamKnows broadband checker, we can get BT Openreach FTTC and FTTP service but not cable-based broadband.
An example check with BT using the address for "Honeypot Nursery, Ujima House, 388 High Road, Wembley, HA9 6AR" we see BT Infinity 2 (76Mbit/19Mbit up) is available. Honeypot Nursery formerly occupied the proposed LHS location and is about 350 feet from the LWWEM Wembley Exchange but seems to actually get service from LWNWEM instead.
- Where do the Ethernet cables pictured in photos 21 and 'ground floor cabinet' go?
Unknown at this time - we'll need to trace where they go in our next visit.
IP's
Currently looking at getting rid of the 172.16.X.Y network and replacing it with a more flexible and expansive 10.20X.X.X IP range.
DNS
TBD -
DHCP
TBD -
IP Allocations
TBD -
TLS
Ideally we've migrated everything to LetsEncrypt unless we're doing internal network / infrastructure SSL trust/validation, but all TBD.
There is a list of our legacy certificates here Networking/TLSCerts
WiFi
We have 6 Cisco 3502 access points, awaiting better locations for Ujima House:
- AP1 -
- AP2 -
- AP3 -
- AP4 -
- AP5 -
- AP6 -
Due to a new version of Cisco IOS the 3502 access points won't let you log in if you present them with loads of ssh pubkeys. To force ssh to use a password use:
ssh -o "PreferredAuthentications password" root@ap1
We have 3 SSID's:
- LondonHackspace - Standard WPA2 auth, the password can be found on notices stuck on the walls of most rooms
- LondonHackspace-5ghz - As above but 5ghz only
- spacenet - part of the SpaceFED Federated inter-hackerspace wifi network, You'll need to setup your LDAP account to use it.
Layer 2
VDSL2 Provider 1
TBD
VDSL2 Provider 2
Local Network
Hopefully we'll have a consistent infrastructure - similar switches for both normal and PoE ethernet, etc.
ToDo
See Networking Todo.
Layer 1 (Physical Wiring)
Ground Floor
Patch Panel
???
First Floor
- 2x Cat6 cables from the ground floor cabinet go up the cable riser and then run above the ceiling tiles into the server room, in cable tray some of the way, see image.
- There are a large number of network sockets spread around the 1st floor, many (all?) of which seem to be run back to a large bundle of cables in the server room, some (all?) of which also run above the ceiling in cable trays.
Patch Panel
???