Cremer st - Infrastructure/Kitchen Wiring: Difference between revisions
From London Hackspace Wiki
No edit summary |
No edit summary |
||
Line 12: | Line 12: | ||
! Purpose !! Power !! Gauge !! Length | ! Purpose !! Power !! Gauge !! Length | ||
|- | |- | ||
| Distro || 100A || 16mm^2|| >>1m+14m+4m = | | Distro || 100A || 16mm^2|| >>1m+14m+4m = 20m | ||
|- | |- | ||
| Oven || 5kW (>>22A) || 4mm^2 || >>2m+2m = 5m | | Oven || 5kW (>>22A) || 4mm^2 || >>2m+2m = 5m | ||
Line 23: | Line 23: | ||
|} | |} | ||
Upgrade diameters (4-6, 16-25) if not clipped to a masonry or wooden wall. | Upgrade diameters (4-6, 16-25) if not clipped to a masonry or wooden wall. | ||
Phil suggests 18m for the 4mm | Phil suggests 18m for the 4mm and 26m for the distro feed | ||
* 50xP-clips for 16mm | * 50xP-clips for 16mm | ||
* 50xP-clips for 4mm | * 50xP-clips for 4mm |
Revision as of 09:29, 16 February 2012
People: Paddyd, Phil, Russ
We have sockets and 2.5mm cable aplenty.
Phil's already done the ring main and water heater circuit, and a few sockets. Ms7821 09:28, 16 February 2012 (UTC)
Planned
- Distro box: 3x32A breakers, 1x16A breaker (6 way suggested, so 2xblank)
- Cables:
Purpose | Power | Gauge | Length |
---|---|---|---|
Distro | 100A | 16mm^2 | >>1m+14m+4m = 20m |
Oven | 5kW (>>22A) | 4mm^2 | >>2m+2m = 5m |
Hob | 6kW/6.6kW (>>29A) | 4mm^2 | >>2m+2m = 5m |
guess 3kW (13A) | 2.5mm^2 | ||
2.5mm^2 |
Upgrade diameters (4-6, 16-25) if not clipped to a masonry or wooden wall. Phil suggests 18m for the 4mm and 26m for the distro feed
- 50xP-clips for 16mm
- 50xP-clips for 4mm
And to finish off the sockets:
- 5x Double dry lining boxes (25mm deep or more)
- 2x single dry lining boxes (any depth)
Suggested suppliers
- TLC-direct (cheap, but whole drum)
- ?
Back-up option
- 2x4mm runs, one for hob, one for oven
- Put boiler on a fused spur or do a separate 2.5/4mm run for that.