'''Important:''' this is not authoritative. It's just a guideline for people who want to understand what's remaining.  Please speak to the [[http://wiki.london.hackspace.org.uk/view/Hackspace_Move#Key_Projects|project contacts]] to find out what the current state is.


== [[Hackspace_Move/Cremer_Restoration|Cremer St Preparations]] ==
* Agree on Cremer St restoration with landlord
* Cremer St cleanup
* Our Cremer Street lease ends on the '''30th April'''
* We need Cremer street to be clear so we can restore it by the 13th/14th
== Hackney Road preparations ==
Access
* <s>Get a locksmith to fit an electronic release on the back door.</s>
* <s>Get override keys cut for every trustee for the back door release.</s>
* <s>Get doorbot installed on the back door, running on an offline card DB. (Looking at Jasper, Mark and Charles here)</s>
Services
* <s>Russ: take initial water & gas meter readings</s> Electric?
* organise rubbish collection (get a skip?)
* Get an internet connection working - this may also require a phone line connecting, although I have a vague memory of Jasper saying the phone was already connected. Basic wifi follows on from this. (Jasper?)
** Phone lines are connected by still being paid for, so we can't take them over.  New line will be fitted 27/3/2013
** FTTC internet ordered from Zen
Decisions
* <s>[[Hackspace_Move/Layout|Finalise layout]]</s>
== [[Hackspace_Move/Renovation|Hackney Road build-out]] ==
* Install the large classroom walls.
*<s> Get a lift engineer out to verify that the lift really is safe to use and place heavy loads in.</s>Insurance issues still to be addressed
* Install ventilation downstairs, <s>routed outside.</s> (Charles?)
*<s> Change current Fire Exit door in basement so it's solid rather than a grill, possibly by panelling with plywood [http://www.flickr.com/photos/hllns/8386735403/ (Pic)]</s>
* Wall off entire fire exit door in basement
* Networking, including patch panels downstairs
== [[Hackspace_Move/Logistics|Hackney Road move]] ==
* Obtain/make equipment for move and fit-out. Moving skates made from scrap wood and castors, Larger ladder for access in new space which has quite a high ceiling
* Start setting up workspaces, workshop, shelves
* MOVE ALL THE THINGS
* '''Deadline''' : 13th/14th April
== PHASE X: Not Time Critical ==
* organise water & gas

Revision as of 19:56, 3 April 2013