Hackspace Move/Planning/2013-04-08

From London Hackspace Wiki

Last week

The basement floor was lifted

 

The drywall erected upstairs

 

And started downstairs

 

Upstairs was rockwalled

 

Gaps filled and sanded, and boxes for sockets installed

 

And started downstairs

 

Run network cabling for the ground floor

 

Got the lift functional, although we still don't have insurance, so please don't use it for travelling in

 

Taken one asbestos-based tile down and put it in the storage room by the main door. Please don't touch it - if you do, contact the trustees.

 

Covered the fire exit to prevent heat escaping. This will be modified again shortly as it's probably intended to be a smoke vent in case of fire.

 


This weekend

Filled the gaps

 

Prepared the concrete

 

To paint the floor

 

Finished product. There are some cracks near the lift that still need filling

 

Removed the chalky paint from the floor of the metal workshop, which will be painted on Monday/Tuesday evening

 

Biohackers are filling gaps for their lab, and will be painting during the week