Hackspace Move/Planning/2013-04-08

From London Hackspace Wiki

Last week

Fixed the ventilation fan motor (which was wired incorrectly)

Erected the drywall upstairs:

 

And rockwalled it

 

Filled and sanded gaps, and installed boxes for sockets

 


Lifted the basement floor

 

And started the partitions

 

Which will also be rockwalled

 


Run network cabling for the ground floor

 

Got the lift functional, although we still don't have insurance, so please don't use it for travelling in

 

Took down one asbestos-based tile and put it in the storage room by the main door. Please don't touch it - if you do, contact the trustees.

 

Covered the fire exit to prevent heat escaping. This will be modified again shortly as it's actually intended to be a smoke vent in case of fire.

 


This weekend

Finished the partitions downstairs

 

Prepared the concrete

 

To paint the floor

 

Painted the floor. There are some cracks near the lift that still need filling

 

Removed the chalky paint from the floor of the metal workshop, which will be painted on Monday/Tuesday evening

 

Filled gaps for the biohacking lab, which will be painted during the week