== Last week ==
== Last week ==


The basement floor was lifted
Erected the drywall upstairs:


[[File:20130329_181326.jpg|400px]]
[[File:20130329_163135.jpg|400px]]
 
And rockwalled it


The drywall erected upstairs
[[File:20130329_163844.jpg|400px]]


[[File:20130329_163135.jpg|400px]]
Filled and sanded gaps, and installed boxes for sockets


And started downstairs
[[File:20130407_200350.jpg|400px]]


[[File:20130329_163356.jpg|400px]]


Upstairs was rockwalled
Lifted the basement floor


[[File:20130329_163844.jpg|400px]]
[[File:20130329_181326.jpg|400px]]


Gaps filled and sanded, and boxes for sockets installed
And started the partitions


[[File:20130407_200350.jpg|400px]]
[[File:20130329_163356.jpg|400px]]


And started downstairs
Which will also be rockwalled


[[File:20130329_163255.jpg|400px]]
[[File:20130329_163255.jpg|400px]]


Run network cabling for the ground floor
Run network cabling for the ground floor
Line 33: Line 35:
[[File:20130406_171659.jpg|400px]]
[[File:20130406_171659.jpg|400px]]


Taken one asbestos-based tile down and put it in the storage room by the main door. Please don't touch it - if you do, contact the trustees.
Took down one asbestos-based tile and put it in the storage room by the main door. Please don't touch it - if you do, contact the trustees.


[[File:20130406_173357.jpg|400px]]
[[File:20130406_173357.jpg|400px]]
Line 43: Line 45:


== This weekend ==
== This weekend ==
Filled the gaps
Finished the partitions downstairs


[[File:20130406_172232.jpg|400px]]
[[File:20130406_172232.jpg|400px]]
Line 55: Line 57:
[[File:20130406_173517.jpg|400px]]
[[File:20130406_173517.jpg|400px]]


Finished product. There are some cracks near the lift that still need filling
Painted the floor. There are some cracks near the lift that still need filling


[[File:20130406_220148.jpg|400px]]
[[File:20130406_220148.jpg|400px]]