Hackspace Move/Planning/2013-04-08
Last week
The basement floor was lifted
The drywall erected upstairs
And started downstairs
Upstairs was rockwalled
Gaps filled and sanded, and boxes for sockets installed
And started downstairs
Run network cabling for the ground floor
Got the lift functional, although we still don't have insurance, so please don't use it for travelling in
Taken one asbestos-based tile down and put it in the storage room by the main door. Please don't touch it - if you do, contact the trustees.
Covered the fire exit to prevent heat escaping. This will be modified again shortly as it's probably intended to be a smoke vent in case of fire.
This weekend
Filled the gaps
Prepared the concrete
To paint the floor
Finished product. There are some cracks near the lift that still need filling
Removed the chalky paint from the floor of the metal workshop, which will be painted on Monday/Tuesday evening
Biohackers are filling gaps for their lab, and will be painting during the week