There is a 48 port patch panel in the cab in the office upstairs, of which 29 ports are used.

The Cab has 7 free U, we need 2 for the switches and 1 for Boole leaving 4...

N.B. new plans depend on working out what we need for new classrooms etc.

Our ISP

80/20 FTTC, 1Tb bandwidth/mo with Zen, see speedtest or [1]

We're getting a native IPv6 only ADSL connection thanks to Andrews & Arnold!

IP's

we have a /29 : 82.69.229.0/29, all are aliased on lo on boole see /etc/iptable/rules for forwarding details

WiFi

We have 6 Cisco 3502 Access points, current deployment:

  • AP1 - office/quiet room - now mounted properly, thanks User:Sully!
  • AP2 - classroom ceiling.
  • AP3 -
  • AP4 -
  • AP5 -
  • AP6 - spare

Ground Floor

Existing

  • 1 - 2 office near window
  • 3 - 4 office under cab
  • 5 office under cab - single socket
  • 6,7,8,9,10,11,12 - classroom
  • 13 - 14 pillar near shower
  • 15 - 16 left of roller door
  • 17 - 18 rear wall of lobby
  • 27 - 28 office under cab
  • 29 - office under cab
  • 30-36 - classroom
  • 37,38 - doorbot
  • 39,40 - near door in office
  • 41,42 - classroom roof, 24 used for ap2
  • +2 more to outside the classroom

4 spaces left on the patch panel!

To be added

Rear Door

Socket needed for doorbot (Wilson) I'd suggest running a double to here done, but may want a direct connection instead.

Quiet room

  • 1 x double socket and a quad - maybe not if we put shelving up.

Classroom 2

Ignoreing this for now.

South Wall Outside the Classroom

  • quad socket by tesla
  • quad socket by the table next to tesla

Both above serve tesla + babbage + printers + other bits

  • dual socket on the east side of the electronics bench
  • and another on the west side
  • dual socket somewhere by the door for future doorbot + other bits <- maybe a quad here?

All the above to go over new trunking, 14 cables.

Classroom

  • sockets on north and west walls done!
  • East wall: 4 x double socket
  • South wall 3 double sockets

all 7 double sockets above to be fed from the trunking on the south side of the horizontal pillar thing along the ceiling == 14 cables, maybe too much to fit?

Basement

Existing

  • 19 - 20 on far wall near hose reel and phone dist boards.
  • 21 - 22 on wall on outside of lift plant room
  • 23 - 24 biohack basement on far wall.
  • 25 - 26 near fire hose pumps hidden behind the desk/counter

To be added

  • 1 x double socket near biohackers door for ac node/doorbot
  • 2 x double socket in each workshop for acnode
  • ?

Total new sockets on the ground floor cabinet

4 between ground and basement 14 in the classroom 14 along south wall -- 36

= 32 new ports needed (4 spare on the existing panels).

but 24 ports a panel, so 2nd new panel with 18 free? or restrict ourselves to 28 new ports?

5 doubles in the classroom 1 quad by tesla and babbage 1 double by tesla and babbage 1 quad by the door?

= 20 + 4 to the basement.