Line 8: Line 8:
 
* Cables:
 
* Cables:
 
{| class="wikitable"
 
{| class="wikitable"
! Purpose !! Power !! Diameter !! Length
+
! Purpose !! Power !! Gauge !! Length
 
|-
 
|-
| Distro || 100A || 16mm || >>1m+14m+4m = 20m
+
| Distro || 100A || 16mm^2|| >>1m+14m+4m = 20m
 
|-
 
|-
| Oven || 5kW (>>22A) || 4mm || >>2m+2m = 5m
+
| Oven || 5kW (>>22A) || 4mm^2 || >>2m+2m = 5m
 
|-
 
|-
| Hob || 6kW/6.6kW (>>29A) || 4mm || >>2m+2m = 5m
+
| Hob || 6kW/6.6kW (>>29A) || 4m^2 || >>2m+2m = 5m
 
|-
 
|-
| Water heater || guess 3kW (13A) || 2.5mm || >>2m = 3m
+
| Water heater || guess 3kW (13A) || 2.5mm^2 || >>2m = 3m
 
|-
 
|-
| Ring main ||  || 2.5mm || >>((2m+2.5m+2.5m)+(2m+2m))*2 = 25m
+
| Ring main ||  || 2.5mm^2 || >>((2m+2.5m+2.5m)+(2m+2m))*2 = 25m
 
|}
 
|}
  

Revision as of 07:47, 16 February 2012

People: Paddyd, Phil, Russ

We have sockets and 2.5mm cable aplenty.

Planned

  • Distro box: 3x32A breakers, 1x16A breaker
  • Cables:
Purpose Power Gauge Length
Distro 100A 16mm^2 >>1m+14m+4m = 20m
Oven 5kW (>>22A) 4mm^2 >>2m+2m = 5m
Hob 6kW/6.6kW (>>29A) 4m^2 >>2m+2m = 5m
Water heater guess 3kW (13A) 2.5mm^2 >>2m = 3m
Ring main 2.5mm^2 >>((2m+2.5m+2.5m)+(2m+2m))*2 = 25m

Upgrade diameters (4-6, 16-25) if not clipped to a masonry or wooden wall.

Suggested suppliers

  • TLC-direct (cheap, but whole drum)
  • ?


Back-up option

  • 2x4mm runs, one for hob, one for oven
  • Put boiler on a fused spur or do a separate 2.5/4mm run for that.