Line 43: Line 43:


* Description: ...
* Description: ...
* Status: Dismantled and removed from Wet Lab.
* Status: Dismantled and removed from Wet Lab. Fans have been kept for possible future use.
* People: ?
* People: ?


Line 49: Line 49:


* Description: ...
* Description: ...
* Status: Clean and tidy, Flushes OK
* Status: Clean and tidy, Flushes OK. Washroom now contains a coat rack for Lab coats, coveralls, aprons etc.
* People: ?
* People: ?


Line 55: Line 55:


* Description: for projections
* Description: for projections
* Status: need to obtain epoxy bolts, then put up screen
* Status: <s> need to obtain epoxy bolts,</s> then put up screen
* People: Adrian (?)
* People: Adrian (?)
* Proposal : drill and epoxy bolts into ceiling near window. Drill auxiliary fixings to hold bolts in place while epoxy sets. After setting, perform pull test on bolts. Schedule team of helpers to lift screen into place and fix. These activities will create some dust, mess and brief disruption in the quiet room.
* Proposal : <s>drill and epoxy bolts into ceiling near window. Drill auxiliary fixings to hold bolts in place while epoxy sets. After setting,</s> (done)  Perform pull test on bolts. Schedule team of helpers to lift screen into place and fix. These activities will create some dust, mess and brief disruption in the quiet room.
* Requirements : epoxy capsules (I have some of these, possibly date-expired - artag), studding, large masonry drill bit, heavy duty power drill. I also have the latter 2, but can't bring them to the space cleaning day. It may be possible to do the drilling phase before that date.
* Requirements : <s>epoxy capsules (I have some of these, possibly date-expired - artag), studding, large masonry drill bit, heavy duty power drill. I also have the latter 2, but can't bring them to the space cleaning day. It may be possible to do the drilling phase before that date.</s>
 
Update 4SEP11
* Progress: Bolts now fixed into ceiling, Mounting plates made and ready.
* Further requirements: Due to revised mounting method more materials as below
 
**4 off M12 full nuts
**4 off <s>M12 flat washers</s> (on site)
**4 off M10 studding 350mm
**16 off M10 full nuts
**16 off M10 flat washers
**4 off strong hackers to lift screen into place
**2 off weak hackers to fit the nuts


=== Quiet Room Projector ===
=== Quiet Room Projector ===


* Description: replace existing projector with the NEC projector, mount it properly
* Description: replace existing projector with the NEC projector, mount it properly
* Status: New mounting part built, to replace a ceiling tile.
* Status: New mounting part built, replaces a ceiling tile. Final detail of mount depends upon geometry of projector to be used.
* People: Phil
* People: Phil