Equipment/High Vacuum Station: Difference between revisions

From London Hackspace Wiki

m
no edit summary
mNo edit summary
mNo edit summary
Line 109: Line 109:
The minimum flow-rate should 75l/h^-1.
The minimum flow-rate should 75l/h^-1.


This suggests that the E04 will need a radiator capable of dispersing 2.2Kw of heat (7512BTU). (NEEDS CHECKING)
As the baffle and valve assembly as also have cooling-loops, some additional capacity should be factored in. No numbers exist for these parts however. As they are indirectly heated however and part of reflux prevention, they perhaps should have a secondary cooling loop or auxiliary radiator between them.


As the baffle and valve assembly as also have cooling-loops, some additional capacity should be factored in. No numbers exist for these parts however. As they are indirectly heated however and part of reflux prevention, they perhaps should have a secondary cooling loop or auxiliary radiator between them.
Estimating any radiator capable of handing about 1Kw should be fine. Several PC water-cooling pumps are within capacity, and variable-speed.
 
Due to likely enclosed location, heat exhaust should be ducted away.


==Progress reports==
==Progress reports==