== PHASE 1: Preparations ==
== Cremer St Preparations ==


* agree on Cremer St restoration with landlord
* Agree on Cremer St restoration with landlord
* Cremer St cleanup
* Cremer St cleanup
* Our Cremer Street lease ends on the '''30th April'''
* Our Cremer Street lease ends on the '''30th April'''
* We need Cremer street to be clear so we can restore it by the 20th/21st April, but 13th/14th would be better.
* We need Cremer street to be clear so we can restore it by the 20th/21st April, but 13th/14th would be better.


== PHASE 2: We receive Keys ==
== Hackney Road preparations ==


Access
Access
* Get a locksmith to fit an electronic release on the back door.
* <s>Get a locksmith to fit an electronic release on the back door.</s>
* Get override keys cut for every trustee for the back door release.
* Get override keys cut for every trustee for the back door release.
* Get doorbot installed on the back door, running on an offline card DB. (Looking at Jasper, Mark and Charles here)
* <s>Get doorbot installed on the back door, running on an offline card DB. (Looking at Jasper, Mark and Charles here)</s>


Infrastructure
Infrastructure
Line 19: Line 19:


Services
Services
* Russ: take initial water & gas meter readings
* <s>Russ: take initial water & gas meter readings</s>
* organise rubbish collection (get a skip?)
* organise rubbish collection (get a skip?)
* Get an internet connection working - this may also require a phone line connecting, although I have a vague memory of Jasper saying the phone was already connected. Basic wifi follows on from this. (Jasper?)
* Get an internet connection working - this may also require a phone line connecting, although I have a vague memory of Jasper saying the phone was already connected. Basic wifi follows on from this. (Jasper?)
** Phone lines are connected by still being paid for, so we can't take them over.  New line will be fitted 27/3/2013
** FTTC internet ordered from Zen


== PHASE 3: We have Fitted Locks & Doorbot ==
== Hackney Road build-out ==


* Obtain/make equipment for move and fit-out. Moving skates made from scrap wood and castors, Larger ladder for access in new space which has quite a high ceiling
* Obtain/make equipment for move and fit-out. Moving skates made from scrap wood and castors, Larger ladder for access in new space which has quite a high ceiling