1,077
edits
(→Power: add ground floor plan) |
|||
Line 29: | Line 29: | ||
== Ventilation == | == Ventilation == | ||
There are currently 2 plans, one for air removal to the outside and the roof, and one for internal filtration. The first plan will require a >£2000 licence to alter for us to implement. | |||
The current choice is to go with filtration unless a licence to alter is required for other build out projects. Initial units have been delivered. | |||
Whatever ventilation plan we end up with, we will also have point extraction at all fixed tools for dust extraction. | |||
== Lift == | == Lift == |
edits