Hackspace Move/Planning/2013-03-25: Difference between revisions

From London Hackspace Wiki
(→‎Power: add ground floor plan)
Line 29: Line 29:
== Ventilation ==
== Ventilation ==


Documentation: [[Hackspace_Move/Workshop_Build]]
There are currently 2 plans, one for air removal to the outside and the roof, and one for internal filtration. The first plan will require a >£2000 licence to alter for us to implement.


(Charles is already asleep, so this is mostly hearsay.)
The current choice is to go with filtration unless a licence to alter is required for other build out projects. Initial units have been delivered.


We've ordered the minimum required kit and it should be delivered on Tuesday.
Whatever ventilation plan we end up with, we will also have point extraction at all fixed tools for dust extraction.
 
There was a discussion about indoor filtering vs actual extraction system; I think we're going for the latter. Charles is planning to use PVC piping, "will ground the hell out of it."