''Things to procure'' | ''Things to procure'' | ||
* | * 8 x Fischer Bolts for 4 mounting legs - 12mm (14?) [also for base] | ||
* Stub for top of mast (39 inner perhaps 40, 57 outer) | |||
* 20+ metres of feeder cable (UHF and HF feeders) | |||
* Post-level (bubble indicator) | |||
* LED strips and Swarovski crystals for decorations | |||
* Pneumatic stuff: | |||
** hoses | ** hoses | ||
** connectors | ** connectors | ||
** electric compressor | ** electric compressor | ||
''Things to do'' | ''Things to do'' | ||
* Fit legs to mast and fit bolts to ground | |||
* Balance mast for easy erection | |||
* run cable between mast top (fully erect) and shack | * run cable between mast top (fully erect) and shack | ||