== Last week == | == Last week == | ||
Fixed the ventilation fan motor (which was wired incorrectly) | |||
Erected the drywall upstairs: | |||
[[File:20130329_163135.jpg|400px]] | |||
And rockwalled it | |||
[[File:20130329_163844.jpg|400px]] | |||
Filled and sanded gaps, and installed boxes for sockets | |||
[[File:20130407_200350.jpg|400px]] | |||
Lifted the basement floor | |||
[[File: | [[File:20130329_181326.jpg|400px]] | ||
And | And started the partitions | ||
[[File: | [[File:20130329_163356.jpg|400px]] | ||
Which will also be rockwalled | |||
[[File:20130329_181051.jpg| | [[File:20130329_163255.jpg|400px]] | ||
Ran some of the network cabling for the ground floor | |||
[[File:20130329_181051.jpg|400px]] | |||
Including Doorbot | |||
[[File:20130320_210834.jpg|400px]] | |||
Got the lift functional, although we still don't have insurance, so please don't use it for travelling in | Got the lift functional, although we still don't have insurance, so please don't use it for travelling in | ||
[[File:20130406_171659.jpg| | [[File:20130406_171659.jpg|400px]] | ||
Took down one asbestos-based tile and put it in the storage room by the main door. Please don't touch it - if you do, contact the trustees or the list. | |||
[[File:20130406_173357.jpg| | [[File:20130406_173357.jpg|400px]] | ||
Covered the fire exit to prevent heat escaping. This will be modified again shortly as it's | Covered the fire exit to prevent heat escaping. This will be modified again shortly as it's actually intended to be a smoke vent in case of fire. | ||
[[File:20130406_172453.jpg| | [[File:20130406_172453.jpg|400px]] | ||
== This weekend == | == This weekend == | ||
Finished the partitions downstairs | |||
[[File:20130406_172232.jpg| | [[File:20130406_172232.jpg|400px]] | ||
Prepared the concrete | Prepared the concrete | ||
[[File:20130406_172603.jpg| | [[File:20130406_172603.jpg|400px]] | ||
To paint the floor | To paint the floor | ||
[[File:20130406_173517.jpg| | [[File:20130406_173517.jpg|400px]] | ||
Painted the floor. There are some cracks near the lift that still need filling | |||
[[File:20130406_220148.jpg| | [[File:20130406_220148.jpg|400px]] | ||
Removed the chalky paint from the floor of the metal workshop, which will be painted on Monday/Tuesday evening | Removed the chalky paint from the floor of the metal workshop, which will be painted on Monday/Tuesday evening | ||
[[File:20130407_190606.jpg| | [[File:20130407_190606.jpg|400px]] | ||
Filled gaps for the biohacking lab, which will be painted during the week | |||
[[File:20130407_190424.jpg|400px]] | |||
[[ | [[Category:Moving_Space]] |
Latest revision as of 20:54, 20 May 2013
Last week
Fixed the ventilation fan motor (which was wired incorrectly)
Erected the drywall upstairs:
And rockwalled it
Filled and sanded gaps, and installed boxes for sockets
Lifted the basement floor
And started the partitions
Which will also be rockwalled
Ran some of the network cabling for the ground floor
Including Doorbot
Got the lift functional, although we still don't have insurance, so please don't use it for travelling in
Took down one asbestos-based tile and put it in the storage room by the main door. Please don't touch it - if you do, contact the trustees or the list.
Covered the fire exit to prevent heat escaping. This will be modified again shortly as it's actually intended to be a smoke vent in case of fire.
This weekend
Finished the partitions downstairs
Prepared the concrete
To paint the floor
Painted the floor. There are some cracks near the lift that still need filling
Removed the chalky paint from the floor of the metal workshop, which will be painted on Monday/Tuesday evening
Filled gaps for the biohacking lab, which will be painted during the week