Hackspace Move/Timeline: Difference between revisions

From London Hackspace Wiki
mNo edit summary
 
(15 intermediate revisions by 6 users not shown)
Line 1: Line 1:
'''Important:''' this is not authoritative. It's just a guideline for people who want to understand what's remaining.  Please speak to the [[http://wiki.london.hackspace.org.uk/view/Hackspace_Move#Key_Projects|project contacts]] to find out what the current state is.
See [[Hackspace_Move/Key_Projects]]


== [[Hackspace_Move/Cremer_Restoration|Cremer St Preparations]] ==
[[Category:Moving_Space]]
 
* Agree on Cremer St restoration with landlord
* Cremer St cleanup
* Our Cremer Street lease ends on the '''30th April'''
* We need Cremer street to be clear so we can restore it by the 20th/21st April, but 13th/14th would be better.
 
== Hackney Road preparations ==
 
Access
* <s>Get a locksmith to fit an electronic release on the back door.</s>
* Get override keys cut for every trustee for the back door release.
* <s>Get doorbot installed on the back door, running on an offline card DB. (Looking at Jasper, Mark and Charles here)</s>
 
Services
* <s>Russ: take initial water & gas meter readings</s>
* organise rubbish collection (get a skip?)
* Get an internet connection working - this may also require a phone line connecting, although I have a vague memory of Jasper saying the phone was already connected. Basic wifi follows on from this. (Jasper?)
** Phone lines are connected by still being paid for, so we can't take them over.  New line will be fitted 27/3/2013
** FTTC internet ordered from Zen
 
Decisions
* [[Hackspace_Move/Layout|Finalise layout]]
 
== [[Hackspace_Move/Renovation|Hackney Road build-out]] ==
* Install the large classroom walls. Not totally necessary, but it might be tricky to have any of our regular meetings without it.
* Get a lift engineer out to verify that the lift really is safe to use and place heavy loads in.
* Install ventilation downstairs, routed outside. (Charles?)
* Install plywood panel(s) in current grill Fire Exit door in basement to stop all the heat escaping outdoors [http://www.flickr.com/photos/hllns/8386735403/ (Pic)]
* Wall off entire fire exit door in basement
 
== [[Hackspace_Move/Logistics|Hackney Road move]] ==
 
* Obtain/make equipment for move and fit-out. Moving skates made from scrap wood and castors, Larger ladder for access in new space which has quite a high ceiling
* Start setting up workspaces, workshop, shelves
* MOVE ALL THE THINGS
* '''Deadline''' : 20th/21st April, but 13th/14th would be better
 
== PHASE X: Not Time Critical ==
 
* organise water & gas

Latest revision as of 20:55, 20 May 2013