|
|
(18 intermediate revisions by 6 users not shown) |
Line 1: |
Line 1: |
| == Cremer St Preparations ==
| | See [[Hackspace_Move/Key_Projects]] |
|
| |
|
| * Agree on Cremer St restoration with landlord
| | [[Category:Moving_Space]] |
| * Cremer St cleanup
| |
| * Our Cremer Street lease ends on the '''30th April'''
| |
| * We need Cremer street to be clear so we can restore it by the 20th/21st April, but 13th/14th would be better.
| |
| | |
| == Hackney Road preparations ==
| |
| | |
| Access
| |
| * <s>Get a locksmith to fit an electronic release on the back door.</s>
| |
| * Get override keys cut for every trustee for the back door release.
| |
| * <s>Get doorbot installed on the back door, running on an offline card DB. (Looking at Jasper, Mark and Charles here)</s>
| |
| | |
| Infrastructure
| |
| * Get a lift engineer out to verify that the lift really is safe to use and place heavy loads in.
| |
| * Install ventilation downstairs, routed outside. (Charles?)
| |
| * Install plywood panel(s) in current grill Fire Exit door in basement to stop all the heat escaping outdoors [http://www.flickr.com/photos/hllns/8386735403/ (Pic)]
| |
| | |
| Services
| |
| * <s>Russ: take initial water & gas meter readings</s>
| |
| * organise rubbish collection (get a skip?)
| |
| * Get an internet connection working - this may also require a phone line connecting, although I have a vague memory of Jasper saying the phone was already connected. Basic wifi follows on from this. (Jasper?)
| |
| ** Phone lines are connected by still being paid for, so we can't take them over. New line will be fitted 27/3/2013
| |
| ** FTTC internet ordered from Zen
| |
| | |
| == Hackney Road build-out ==
| |
| * Install the large classroom walls. Not totally necessary, but it might be tricky to have any of our regular meetings without it.
| |
| | |
| == Hackney Road move ==
| |
| | |
| * Obtain/make equipment for move and fit-out. Moving skates made from scrap wood and castors, Larger ladder for access in new space which has quite a high ceiling
| |
| * Start setting up workspaces, workshop, shelves
| |
| * MOVE ALL THE THINGS
| |
| * '''Deadline''' : 20th/21st April, but 13th/14th would be better
| |
| | |
| == PHASE X: Not Time Critical ==
| |
| | |
| * organise water & gas
| |