| '''Important:''' this is not authoritative. It's just a guideline for people who want to understand what's remaining. Please speak to the [[http://wiki.london.hackspace.org.uk/view/Hackspace_Move#Key_Projects|project contacts]] to find out what the current state is.
| | See [[Hackspace_Move/Key_Projects]] |
|
| |
|
| == [[Hackspace_Move/Cremer_Restoration|Cremer St Preparations]] ==
| | [[Category:Moving_Space]] |
| | |
| * Agree on Cremer St restoration with landlord
| |
| * Cremer St cleanup
| |
| * Our Cremer Street lease ends on the '''30th April'''
| |
| * We need Cremer street to be clear so we can restore it by the 13th/14th
| |
| | |
| == Hackney Road preparations ==
| |
| | |
| Access
| |
| * <s>Get a locksmith to fit an electronic release on the back door.</s>
| |
| * Get override keys cut for every trustee for the back door release.
| |
| * <s>Get doorbot installed on the back door, running on an offline card DB. (Looking at Jasper, Mark and Charles here)</s>
| |
| | |
| Services
| |
| * <s>Russ: take initial water & gas meter readings</s>
| |
| * organise rubbish collection (get a skip?)
| |
| * Get an internet connection working - this may also require a phone line connecting, although I have a vague memory of Jasper saying the phone was already connected. Basic wifi follows on from this. (Jasper?)
| |
| ** Phone lines are connected by still being paid for, so we can't take them over. New line will be fitted 27/3/2013
| |
| ** FTTC internet ordered from Zen
| |
| | |
| Decisions
| |
| * <s>[[Hackspace_Move/Layout|Finalise layout]]</s>
| |
| | |
| == [[Hackspace_Move/Renovation|Hackney Road build-out]] ==
| |
| * Install the large classroom walls.
| |
| * Get a lift engineer out to verify that the lift really is safe to use and place heavy loads in.
| |
| * Install ventilation downstairs, <s>routed outside.</s> (Charles?)
| |
| * Change current Fire Exit door in basement so it's solid rather than a grill, possibly by panelling with plywood [http://www.flickr.com/photos/hllns/8386735403/ (Pic)]
| |
| * Networking, including patch panels downstairs
| |
| | |
| == [[Hackspace_Move/Logistics|Hackney Road move]] ==
| |
| | |
| * Obtain/make equipment for move and fit-out. Moving skates made from scrap wood and castors, Larger ladder for access in new space which has quite a high ceiling
| |
| * Start setting up workspaces, workshop, shelves
| |
| * MOVE ALL THE THINGS
| |
| * '''Deadline''' : 13th/14th April
| |
| | |
| == PHASE X: Not Time Critical ==
| |
| | |
| * organise water & gas
| |