Line 47: | Line 47: | ||
* power sockets? (not critical? - but they will need a fridge from day one?). | * power sockets? (not critical? - but they will need a fridge from day one?). | ||
+ | |||
+ | == internets == | ||
+ | |||
+ | * <s>fttc</s> | ||
+ | * config an access point | ||
+ | ** test it | ||
+ | ** clone config to other ap's |
Revision as of 13:52, 10 April 2013
ground floor
class room
- fit power and network sockets in the new walls
- finish new walls.
lift and fix broken bits of floorwill probably need the shelving removed
- finish a few trunking bits
- fit access point to ceiling
- paint walls:
- what colour? plain matt white?
elsewhere
- more network sockets
- more power sockets
- clean under windows. - 1/4 done
quiet room
- run network to basement
- fit access point.
- move shelves
- paint walls? (they are a bit manky atm)
back door area
fix doorlock (please!).- finish some trunking bits.
- finish boxing in doorbot.
basement
fix heating.- run and fit power
- run network down from the ground floor - 8 cables
finish rockwooling- finish walls
- fit air filters
- power and network sockets in walls
- run cables to access points (on ceiling).
- paint walls
clean floorpaint floor
biohacker room
- power sockets? (not critical? - but they will need a fridge from day one?).
internets
fttc- config an access point
- test it
- clone config to other ap's