Hackspace Move/Electronics: Difference between revisions
From London Hackspace Wiki
mNo edit summary |
|||
Line 23: | Line 23: | ||
The etch tank needs ventilation, running water and drainage, hence the plan is to locate it downstairs between the biolab and the lift shaft. | The etch tank needs ventilation, running water and drainage, hence the plan is to locate it downstairs between the biolab and the lift shaft. | ||
[[Category:Moving_Space]] |
Latest revision as of 20:53, 20 May 2013
Responsible: mentar
Dependencies
- Ventilation (Paddy, Steve, Charles)
- Mild HCL fumes likely during etching, filter must be able to deal with these
- Drainage (none!) - Normal requirements for etching, HCL not strong enough to warrant special treatment
- Power (alisonw)
- Comms (Jasper/tgreer) - Running water supply for etching
Logistics
Electronics related equipment and components have been packed in boxes labeled as "Electronics" or encircled "E"
Some Radio stuff is being moved along with the electronics equipment. Please stack nearby.
Electronics stations
The plan is to have 2 soldering and 1 test bench upstairs
Etching station
The etch tank needs ventilation, running water and drainage, hence the plan is to locate it downstairs between the biolab and the lift shaft.