ground floor
class room
fit power and network sockets in the new walls
finish new walls.
lift and fix broken bits of floor: will probably need the shelving removed
finish a few trunking bits
fit access point to ceiling
paint walls: what colour? plain matt white?
elsewhere
more network sockets more power sockets clean under windows. - 1/4 done
quiet room
run network to basement fit access point. move shelves paint walls? (they are a bit manky atm)
back door area
fix doorlock (please!).finish some trunking bits. finish boxing in doorbot.
basement
fix heating.run and fit power run network down from the ground floor - 8 cables
finish rockwoolingfinish walls power and network sockets in walls run cables to access points (on ceiling). paint wallsclean floorpaint floor
biohacker room
power sockets? (not critical? - but they will need a fridge from day one?).