Hackspace Move/TODO
< Hackspace Move
Jump to navigation
Jump to search
Revision as of 18:28, 10 April 2013 by JasperWallace (talk | contribs)
Pre Move
All this stuff needs to be done before we can officially open
Ground Floor
Classroom
- fit power and network sockets in the new walls
- finish new walls.
lift and fix broken bits of floorwill probably need the shelving removed
- finish a few trunking bits
- fit access point to ceiling
- paint walls:
- what colour? plain matt white?
Lobby
- fix doorbell
Elsewhere
- more network sockets
- more power sockets
- clean under windows. - 1/4 done
quiet room
- run network to basement
- fit access point.
- move shelves
- paint walls? (they are a bit manky atm)
Back door area
fix doorlock (please!).- finish some trunking bits.
- finish boxing in doorbot.
Basement
Workshop
- Filler walls
- Sand walls
- Paint walls
- Paint metal shop floor
- Clad miniworkshop walls
- Put up power/network trunking
- Place tools
- Place sockets/run cable
- Run extraction to tools
- Automate filtration
- Run plumbing to workshop sink/biolab
biohacker room
- power sockets
internets
fttcconfig an access pointtest itclone config to other ap's- mount access points tidly
Post Move
This is a list of things that arn't vital to the space function but need to get done
Ground floor
Classroom
- Fit projector screen
- Fit projector
- Led board
elsewhere
- lasercutter
Lobby Area
- signage
basement
- Led board
Internets
- fit and fix the bandwidth meter
- spacefed
- v6 tunnel (?)
- A&A v6
- bufferbloat kernel and tuning
- bandwidth management of some kind.