Hackspace Move/Timeline: Difference between revisions

From London Hackspace Wiki
(add some dates)
mNo edit summary
 
(22 intermediate revisions by 7 users not shown)
Line 1: Line 1:
== PHASE 1: Preparations ==
See [[Hackspace_Move/Key_Projects]]


* agree on Cremer St restoration with landlord
[[Category:Moving_Space]]
* Cremer St cleanup
 
== PHASE 2: We receive Keys ==
 
Access
* Get a locksmith to fit an electronic release on the back door.
* Get override keys cut for every trustee for the back door release.
* Get doorbot installed on the back door, running on an offline card DB. (Looking at Jasper, Mark and Charles here)
 
Infrastructure
* Get a lift engineer out to verify that the lift really is safe to use and place heavy loads in.
* Install ventilation downstairs, routed outside. (Charles?)
* Install plywood panel(s) in current grill Fire Exit door in basement to stop all the heat escaping outdoors [http://www.flickr.com/photos/hllns/8386735403/ (Pic)]
 
Services
* Russ: take initial water & gas meter readings
* organise rubbish collection (get a skip?)
* Get an internet connection working - this may also require a phone line connecting, although I have a vague memory of Jasper saying the phone was already connected. Basic wifi follows on from this. (Jasper?)
 
== PHASE 3: We have Fitted Locks & Doorbot ==
 
* Obtain/make equipment for move and fit-out. Moving skates made from scrap wood and castors, Larger ladder for access in new space which has quite a high ceiling
* Start setting up workspaces, workshop, shelves
* MOVE ALL THE THINGS
* '''Deadline''' : 20th/21st April, but 13th/14th would be better
 
== PHASE X: Not Time Critical ==
 
* organise water & gas
* Possibly install the large classroom walls. Not totally necessary, but it might be tricky to have any of our regular meetings without it.

Latest revision as of 20:55, 20 May 2013