Hackspace Move/Key Projects: Difference between revisions
From London Hackspace Wiki
No edit summary |
mNo edit summary |
||
(9 intermediate revisions by 6 users not shown) | |||
Line 9: | Line 9: | ||
**<s> Get a lift engineer out to verify that the lift really is safe to use and place heavy loads in. </s>Insurance issues still to be addressed | **<s> Get a lift engineer out to verify that the lift really is safe to use and place heavy loads in. </s>Insurance issues still to be addressed | ||
* '''Power*''': alisonw (Charles - workshop) | * '''Power*''': alisonw (Charles - workshop) | ||
* Door access: Mark/ms7821, tgreer | * <s>Door access: Mark/ms7821, tgreer | ||
** Doorbot is installed. Trustees have override keys. | |||
** And at old space.</s> | |||
* Comms: Jasper, Thomas/tgreer ([[447_Hackney_Road/Networking]]) | * Comms: Jasper, Thomas/tgreer ([[447_Hackney_Road/Networking]]) | ||
** Phone lines are connected by still being paid for, so we can't take them over. New line will be fitted 27/3/2013 | ** <s>Phone lines are connected by still being paid for, so we can't take them over. New line will be fitted 27/3/2013</s> phone line now live | ||
** FTTC internet ordered from Zen | ** <s>FTTC internet ordered from Zen - will be done next week, Weds 10th AM.</s> done | ||
* Waste: Jasper | * Waste: Jasper | ||
* (Drainage) | * (Drainage) | ||
Line 19: | Line 21: | ||
== Hackney Rd, legal/regulations == | == Hackney Rd, legal/regulations == | ||
* Fire safety (exits, extinguishers, lighting, etc): Russ | * Fire safety (exits, extinguishers, lighting, etc): Russ | ||
* Accessibility: | * Accessibility: | ||
== Hackney Rd, functional areas == | == Hackney Rd, functional areas == | ||
* Workshop: Charles/solexious | * Workshop: Charles/solexious | ||
** Floor has received first coat of paint! (Excepting the dirty metalworking room, to be done later) | |||
** Walls are constructed for woodworking and dirty metalworking rooms. | |||
* Wetlab: Will/will-h, biohackers | * Wetlab: Will/will-h, biohackers | ||
* [[Hackspace_Move/Electronics|Electronics(incl EtchTank)]]: Eugene/mentar | * [[Hackspace_Move/Electronics|Electronics(incl EtchTank)]]: Eugene/mentar | ||
Line 35: | Line 38: | ||
* Cleanup | * Cleanup | ||
* Packing | * Packing | ||
** Kitchen, quiet room: Marc B. | |||
** Workshop: (Duffy?) | |||
** Social area: | |||
** Lobby area: | |||
* Agree on Cremer St restoration with landlord | * Agree on Cremer St restoration with landlord | ||
* Restoration | * [[Hackspace_Move/Cremer_Restoration|Restoration]] | ||
Our Cremer Street lease ends on the '''30th April'''. | Our Cremer Street lease ends on the '''30th April'''. | ||
Line 51: | Line 58: | ||
* organise water & gas | * organise water & gas | ||
[[Category:Moving_Space]] |
Latest revision as of 20:56, 20 May 2013
A number of key activities and the people coordinating them. Highlighted* projects have been identified as critical: they are prerequisites for other work, or they establish what we can initially do at the space.
Important: project statuses are not authoritative. Please speak to the project contact to find out what the current state is.
Hackney Rd, basic infrastructure
- Walls*: Paddy, Steve (Charles - workshop)
- Ventilation*: Paddy, Steve, Charles
- Lift*: Thomas/tgreer
Get a lift engineer out to verify that the lift really is safe to use and place heavy loads in.Insurance issues still to be addressed
- Power*: alisonw (Charles - workshop)
Door access: Mark/ms7821, tgreer- Doorbot is installed. Trustees have override keys.
And at old space.
- Comms: Jasper, Thomas/tgreer (447_Hackney_Road/Networking)
Phone lines are connected by still being paid for, so we can't take them over. New line will be fitted 27/3/2013phone line now liveFTTC internet ordered from Zen - will be done next week, Weds 10th AM.done
- Waste: Jasper
- (Drainage)
- (Flooring)
Hackney Rd, legal/regulations
- Fire safety (exits, extinguishers, lighting, etc): Russ
- Accessibility:
Hackney Rd, functional areas
- Workshop: Charles/solexious
- Floor has received first coat of paint! (Excepting the dirty metalworking room, to be done later)
- Walls are constructed for woodworking and dirty metalworking rooms.
- Wetlab: Will/will-h, biohackers
- Electronics(incl EtchTank): Eugene/mentar
- Darkroom: wyan
- "Music" or performance space (actual form tbd)
- Classroom
- Storage, shelves
Cremer St
- Pre-move (early removal of excess kit to 447 or give away): Thomas/tgreer
- Cleanup
- Packing
- Kitchen, quiet room: Marc B.
- Workshop: (Duffy?)
- Social area:
- Lobby area:
- Agree on Cremer St restoration with landlord
- Restoration
Our Cremer Street lease ends on the 30th April.
The actual move
- Loading:
- Transport: Thomas/tgreer
- Unloading: Sam/Eithin
- Set-up:
- Deadline: 13th/14th April
PHASE X: Not Time Critical
- organise water & gas