A number of key activities and the people coordinating them. '''Highlighted*''' projects have been identified as critical: they are prerequisites for other work, or they establish what we can initially do at the space. | A number of key activities and the people coordinating them. '''Highlighted*''' projects have been identified as critical: they are prerequisites for other work, or they establish what we can initially do at the space. | ||
'''Important:''' project statuses are not authoritative. Please speak to the project contact to find out what the current state is. | |||
== Hackney Rd, basic infrastructure == | == Hackney Rd, basic infrastructure == | ||
Line 5: | Line 7: | ||
* '''[[447_Hackney_Road/Ventilation|Ventilation]]*''': Paddy, Steve, Charles | * '''[[447_Hackney_Road/Ventilation|Ventilation]]*''': Paddy, Steve, Charles | ||
* '''Lift*''': Thomas/tgreer | * '''Lift*''': Thomas/tgreer | ||
**<s> Get a lift engineer out to verify that the lift really is safe to use and place heavy loads in. </s>Insurance issues still to be addressed | |||
* '''Power*''': alisonw (Charles - workshop) | * '''Power*''': alisonw (Charles - workshop) | ||
* Door access: Mark/ms7821, tgreer | * Door access: Mark/ms7821, tgreer | ||
* Comms: Jasper, Thomas/tgreer ([[447_Hackney_Road/Networking]]) | * Comms: Jasper, Thomas/tgreer ([[447_Hackney_Road/Networking]]) | ||
** Phone lines are connected by still being paid for, so we can't take them over. New line will be fitted 27/3/2013 | |||
** FTTC internet ordered from Zen | |||
* Waste: Jasper | * Waste: Jasper | ||
* (Drainage) | * (Drainage) | ||
Line 14: | Line 19: | ||
== Hackney Rd, legal/regulations == | == Hackney Rd, legal/regulations == | ||
* Fire safety (exits, extinguishers, lighting, etc): Russ | * Fire safety (exits, extinguishers, lighting, etc): Russ | ||
** Wall off entire fire exit door in basement? | |||
* Accessibility: | * Accessibility: | ||
Line 29: | Line 35: | ||
* Cleanup | * Cleanup | ||
* Packing | * Packing | ||
* Agree on Cremer St restoration with landlord | |||
* Restoration | * Restoration | ||
Our Cremer Street lease ends on the '''30th April'''. | |||
== The actual move == | == The actual move == | ||
[[Hackspace_Move/RegisterToHelp | Register to help out!]] | |||
* Loading: | * Loading: | ||
* Transport: Thomas/tgreer | * Transport: Thomas/tgreer | ||
* Unloading: Sam/Eithin | * Unloading: Sam/Eithin | ||
* Set-up: | * Set-up: | ||
* '''Deadline: 13th/14th April''' | |||
== PHASE X: Not Time Critical == | |||
* organise water & gas |
Revision as of 19:55, 3 April 2013
A number of key activities and the people coordinating them. Highlighted* projects have been identified as critical: they are prerequisites for other work, or they establish what we can initially do at the space.
Important: project statuses are not authoritative. Please speak to the project contact to find out what the current state is.
Hackney Rd, basic infrastructure
- Walls*: Paddy, Steve (Charles - workshop)
- Ventilation*: Paddy, Steve, Charles
- Lift*: Thomas/tgreer
Get a lift engineer out to verify that the lift really is safe to use and place heavy loads in.Insurance issues still to be addressed
- Power*: alisonw (Charles - workshop)
- Door access: Mark/ms7821, tgreer
- Comms: Jasper, Thomas/tgreer (447_Hackney_Road/Networking)
- Phone lines are connected by still being paid for, so we can't take them over. New line will be fitted 27/3/2013
- FTTC internet ordered from Zen
- Waste: Jasper
- (Drainage)
- (Flooring)
Hackney Rd, legal/regulations
- Fire safety (exits, extinguishers, lighting, etc): Russ
- Wall off entire fire exit door in basement?
- Accessibility:
Hackney Rd, functional areas
- Workshop: Charles/solexious
- Wetlab: Will/will-h, biohackers
- Electronics(incl EtchTank): Eugene/mentar
- Darkroom: wyan
- "Music" or performance space (actual form tbd)
- Classroom
- Storage, shelves
Cremer St
- Pre-move (early removal of excess kit to 447 or give away): Thomas/tgreer
- Cleanup
- Packing
- Agree on Cremer St restoration with landlord
- Restoration
Our Cremer Street lease ends on the 30th April.
The actual move
- Loading:
- Transport: Thomas/tgreer
- Unloading: Sam/Eithin
- Set-up:
- Deadline: 13th/14th April
PHASE X: Not Time Critical
- organise water & gas